How the duration is worked out
Days = amount of work ÷ (output per worker per day × workers)
A worked example
Thirty squares of roofing, with three workers each laying 4 squares a day, is 12 squares a day. The job takes 2.5 days, so plan for 3. That is 60 labor hours.
Good to know
- Use your own crew's numbers from past jobs. Production rates vary hugely with the pitch of the roof, access, weather and how cut-up the work is.
- Doubling the crew rarely halves the time. People get in each other's way, and some tasks cannot be split.
- Add time for setup, cleanup, deliveries and inspections. They are real days even though no production happens.
- Feed the labor hours into the labor cost calculator to price the job.
Common questions
How do I find my production rate?
Take a finished job, divide the amount of work by the number of worker-days it took, and keep a note. After a few jobs you will have a reliable figure.
How we know this calculator is right
Before this calculator went on the site, 8 answers were worked out separately from its code, by hand or straight from the formula above. Each time this page loads, your own browser runs the calculator on those same numbers and compares. Turn on JavaScript to see the comparison.
See every check
| Numbers used | Result | Worked out separately | This calculator |
|---|
What this proves: the calculator does the arithmetic of the formula shown, correctly. What it cannot prove: your measurements, or figures such as coverage per bag, waste and spacing, which are typical starting values you can change. Go by the product label and your local code.